More Projects

EPIC for Consolidated Pipeline/Piping Replacement Works (Combined Package A & Package B)

Marina Towers Development

Afjat Muaither RPS and Associated Pipelines

Rehabilitation / Reconstruction of Selected Awka Roads

MOF Jetty II Extension Project

Maintain Potential Program

Diyab Gas Export Pilot Project (TOTAL Unconventional Gas) The Installation of 8” CS Pipeline

Location: Al Ruwais, United Arab Emirates

Client: TOTAL Energies

Value: $25M – $75M

Timeline: 18 months

Scope: Diyab Gas Export Pilot Project (TOTAL Unconventional Gas) The Installation of 8” CS Pipeline; to install a new 8”(length of approx. 35Km) gas pipeline from EPF to the tie-in location at the Beach Valve Station to make use of the flare gas to limit the environmental impact of burning

Unique Challenge Full automatic welding. Short-duration contract completed in time during Covid-19 restrictions

Client Satisfaction / Awards: Yes

C.A.T. Business Goals: Building trust with new client

Local Resources: Partly sourced from local manufacturers

Safety: 800,000 Man hours without incidents

More Projects

EPIC for Consolidated Pipeline/Piping Replacement Works (Combined Package A & Package B)

Afjat Muaither RPS and Associated Pipelines

Project Gallery