Location: KSA – Riyadh area – East/West Corridor
Client: Saudi Aramco
Value: Over $250M
Timeline: 2014-2019. 5 Years & 10 Months
Scope Included:
- Engineering, procurement, and construction of a 310Km of 56-inch gas pipeline in 3 sections
 - 6 launcher/receiver stations
 - 19 sectionalizing valve stations with the drain and fire pits
 - Power and control systems including solar panels
 - SCADA and gas leak detection systems.
 
Unique Challenges:
- Terrain – Unique challenges regarding harsh geographical areas, consisting of steep mountains and high-flood areas.
 - Logistics – Extremely long delivery distances for pipes and other facilities
 - Sourcing – Large valve delivery
 - Availability of water for hydro test activities
 - Excavation – micro tunneling work under existing highways (19 locations)
 - Interpersonal – Relationship management with various authorities and private landowners
 
C.A.T. Business Goals:
- Aim – Required to deliver project despite multiple challenges and related financial deviations
 - Response – Perseverance through adversity resulted in high-quality being achieved – client trust was secured and multiple additional projects awarded
 
Local Resources: Remit to meet 15% employment of local resources. Awarded Saudization certificate on exceeding the stipulated requirement
Safety Matters: The project was delivered without lost time injury, plus achieved multiple safety awards, certificates, and appreciation gatherings were conducted for employees
Client Satisfaction/Awards: Met client satisfaction / Achieved several safety awards